Production monitoring system
October 29, 2023 ⚊ 1 Min read ⚊ Views 47 ⚊ BLOGLeanworx production monitoring reports highlighted a number of problems. In the first couple of days it was found that the last 2 to 3 hours in the night shift showed zero production. This too resolved itself. Waiting for raw material was a common cause of downtime that as identified, focused upon and reduced. Rejections in a few CNC machines and in the mould making were high, and were reduced. Frequent breakdowns in some old CNC machines and in the air supply to core shooters were identified as key causes of reduction in availability.